- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
- 81
- 82
- 83
- 84
- 85
- 86
- 87
- 88
- 89
- 90
- 91
- 92
- 93
- 94
- 95
- 96
- 97
- 98
- 99
- 100
Information
Quiz description Scrum Master Certified I. 500 questions (1 – 100)
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 100 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
- 81
- 82
- 83
- 84
- 85
- 86
- 87
- 88
- 89
- 90
- 91
- 92
- 93
- 94
- 95
- 96
- 97
- 98
- 99
- 100
- Answered
- Review
-
Question 1 of 100
1. Question
1 pointsThe Sprint Backlog and the Sprint Goal are the results of Sprint Planning.
Correct
Congrats! 1.
Incorrect
-
Question 2 of 100
2. Question
1 pointsWhat should the Scrum Master do, if the Scrum Team does not have the tools and infrastructure required for the development of items?
Correct
Congrats! 2.
Incorrect
-
Question 3 of 100
3. Question
1 pointsWhich activities will a Product Owner likely engage in during a Sprint? Select three answers.
Correct
Congrats! 3. 4. 5.
Incorrect
-
Question 4 of 100
4. Question
1 pointsWhich of the following is true about the Scrum Master role? Select two answers.
Correct
Congrats! 1. 5.
Incorrect
-
Question 5 of 100
5. Question
1 pointsScrum framework consists of… Select two answers.
Correct
Congrats! 2. 4.
Incorrect
-
Question 6 of 100
6. Question
1 pointsScrum is a technique.
Correct
Congrats! 1.
Incorrect
-
Question 7 of 100
7. Question
1 pointsA Scrum Team failed to meet the Sprint objectives. One of the key members of the Development Team fell ill and was away for 3 days right at the beginning of the 4-week Sprint. What is the most likely reason that the Team did not meet the Sprint objectives?
Correct
Congrats! 3.
Incorrect
-
Question 8 of 100
8. Question
1 pointsHow should “Done” be defined when multiple Scrum Teams are working on a single product?
Correct
Congrats! 3.
Incorrect
-
Question 9 of 100
9. Question
1 pointsWhich of the following are feedback loops in Scrum? Select three answers.
Correct
Congrats! 1. 2. 5.
Incorrect
-
Question 10 of 100
10. Question
1 pointsWhat is the time-box for a Sprint Review?
Correct
Congrats! 1.
Incorrect
-
Question 11 of 100
11. Question
1 pointsWhy does the Development Team need a Sprint Goal?
Correct
Congrats! 3.
Incorrect
-
Question 12 of 100
12. Question
1 pointslf burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?
Correct
Congrats! 4.
Incorrect
-
Question 13 of 100
13. Question
1 pointsWhen do Development Team members take ownership of a Sprint Backlog item?
Correct
Congrats! 3.
Incorrect
-
Question 14 of 100
14. Question
1 pointsWhen is a Product Backlog ítem considered complete?
Correct
Congrats! 2.
Incorrect
-
Question 15 of 100
15. Question
1 pointslf burndown charts are used to visualize progress, what do they track?
Correct
Congrats! 4.
Incorrect
-
Question 16 of 100
16. Question
1 pointsWhen many Scrum Teams are working on the same product, should all of their increments be integrated in every Sprint?
Correct
Congrats! 2.
Incorrect
-
Question 17 of 100
17. Question
1 pointsWhat does the Scrum Development Team attempt to develop at every Sprint?
Correct
Congrats! 4.
Incorrect
-
Question 18 of 100
18. Question
1 pointsWhich of the following meeting is not part of Scrum?
Correct
Congrats! 3.
Incorrect
-
Question 19 of 100
19. Question
1 pointsThe purpose of a Sprint is to have a working increment of product done before the Sprint Review.
Correct
Congrats! 1.
Incorrect
-
Question 20 of 100
20. Question
1 pointsWho determines whether the development team has been assigned enough work in a Sprint?
Correct
Congrats! 1.
Incorrect
-
Question 21 of 100
21. Question
1 pointsWhich statement best describes what it means for an activity to be time-boxed?
Correct
Congrats! 3.
Incorrect
-
Question 22 of 100
22. Question
1 pointsFrom the activities given, which is the latest step in sequence of the Scrum framework?
Correct
Congrats! 2.
Incorrect
-
Question 23 of 100
23. Question
1 pointsWhat is the major difference between Product Backlog and Sprint Backlog?
Correct
Congrats! 3.
Incorrect
-
Question 24 of 100
24. Question
1 pointsA sustainable pace means…
Correct
Congrats! 3.
Incorrect
-
Question 25 of 100
25. Question
1 pointsWhich is the Scrum way of doing things?
Correct
Congrats! 1.
Incorrect
-
Question 26 of 100
26. Question
1 pointsThe Product Owner role in Scrum…
Correct
Congrats! 2.
Incorrect
-
Question 27 of 100
27. Question
1 pointsWhich of the following is not a Product Owner’s responsibility?
Correct
Congrats! 4.
Incorrect
-
Question 28 of 100
28. Question
1 pointsOne of the development stages you would expect to see a team go through is…
Correct
Congrats! 1.
Incorrect
-
Question 29 of 100
29. Question
1 pointsWhat is mainly defined by the Scrum Framework? Select two answers.
Correct
Congrats! 1. 4.
Incorrect
-
Question 30 of 100
30. Question
1 pointsWhen handling team dynamics, what should the Scrum Master do?
Correct
Congrats! 1.
Incorrect
-
Question 31 of 100
31. Question
1 pointsWhat is the effect of having a large visible story board on a wall?
Correct
Congrats! 2.
Incorrect
-
Question 32 of 100
32. Question
1 pointsWhat are the major properties of a cross-functional Development Team?
Correct
Congrats! 2.
Incorrect
-
Question 33 of 100
33. Question
1 pointsThe length of a Sprint should be…
Correct
Congrats! 4.
Incorrect
-
Question 34 of 100
34. Question
1 pointsWhat is the role of Management in Scrum?
Correct
Congrats! 3.
Incorrect
-
Question 35 of 100
35. Question
1 pointsIt is mandatory that the product increment be released to production at the end of each Sprint.
Correct
Congrats! 2.
Incorrect
-
Question 36 of 100
36. Question
1 pointsDuring a Sprint, a Development Team determines that it will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?
Correct
Congrats! 1.
Incorrect
-
Question 37 of 100
37. Question
1 pointsWhich statement best describes a Product Owner’s responsibility?
Correct
Congrats! 1.
Incorrect
-
Question 38 of 100
38. Question
1 pointsWho is responsible for monitoring progress toward high-level goals?
Correct
Congrats! 1.
Incorrect
-
Question 39 of 100
39. Question
1 pointsThe structure of the Daily Scrum is well-defined and constant. Every team member should answer the three main questions: What did I do yesterday? What will I do today? Do I see any impediment?
Correct
Congrats! 2.
Incorrect
-
Question 40 of 100
40. Question
1 pointsIn which meetings the Key Stakeholders are allowed to participate?
Correct
Congrats! 2.
Incorrect
-
Question 41 of 100
41. Question
1 pointsWho has the authority to cancel the Sprint?
Correct
Congrats! 5.
Incorrect
-
Question 42 of 100
42. Question
1 pointsWhat belongs solely to the Development Team?
Correct
Congrats! 4.
Incorrect
-
Question 43 of 100
43. Question
1 pointsWho is responsible for tracking the total work remaining in the Sprint Backlog to project the likelihood of achieving the Sprint Goal?
Correct
Congrats! 5.
Incorrect
-
Question 44 of 100
44. Question
1 pointsWho is responsible for all estimates in the Product Backlog?
Correct
Congrats! 2.
Incorrect
-
Question 45 of 100
45. Question
1 pointsWhich statement is true about the projects which has multiple teams?
Correct
Congrats! 1.
Incorrect
-
Question 46 of 100
46. Question
1 pointsEven though the Scrum Team is following the Scrum framework entirely and their project is going well, the organization as a whole does not have a good understanding of Scrum, which makes some troubles for the Scrum Team. Who should try to fix it?
Correct
Congrats! 2.
Incorrect
-
Question 47 of 100
47. Question
1 pointsA Scrum Master has a list of open impediments which is growing without proper resolutions. The Scrum Master consults with the Development Team on the problem. Is it right?
Correct
Congrats! 1.
Incorrect
-
Question 48 of 100
48. Question
1 pointsFor a Scrum Team, the Sprint Planning meetings are always going beyond the time-boxing. What could be the likely causes? Select two answers.
Correct
Congrats! 2. 3.
Incorrect
-
Question 49 of 100
49. Question
1 pointsThe formal opportunities for Inspection and Adaptation are…
Correct
Congrats! 4.
Incorrect
-
Question 50 of 100
50. Question
1 pointsHow many hours per day should a Development Team member work?
Correct
Congrats! 2.
Incorrect
-
Question 51 of 100
51. Question
1 pointsWhat are the three most applicable characteristics of the Product Owner? Select three answers.
Correct
Congrats! 1. 3. 5.
Incorrect
-
Question 52 of 100
52. Question
1 pointsA senior manager frequently distracts the team. Who should try to solve this problem?
Correct
Congrats! 2.
Incorrect
-
Question 53 of 100
53. Question
1 pointsDevelopment Team maintains a Sprint burn-down to track estimated remaining work. In the middle of the Sprint, the burn down graph shows an upward spike. This indicates…
Correct
Congrats! 3.
Incorrect
-
Question 54 of 100
54. Question
1 pointsWhich of the following is required by Scrum? Select two answers.
Correct
Congrats! 1. 2.
Incorrect
-
Question 55 of 100
55. Question
1 pointsA Product Owner wants a story to be completed in two days. The Development Team member working on the Story reckons it will take five days. The Scrum Master feels it should take three days. A subject matter expert, who has worked on similar Stories in the past, thinks it should be at most a one day effort. Whose estimate should be used for planning?
Correct
Congrats! 4.
Incorrect
-
Question 56 of 100
56. Question
1 pointsA Scrum Team selects a Product Backlog Item (PBI) for the Sprint Backlog. What must the Development Team do to finish the Product Backlog Item it selects?
Correct
Congrats! 2.
Incorrect
-
Question 57 of 100
57. Question
1 pointsWhich outcome is expected as Scrum Teams mature?
Correct
Congrats! 1.
Incorrect
-
Question 58 of 100
58. Question
1 pointsWhich technique is the least productive way the Scrum Master can ensure that the Development Team communicates effectively with the Product Owner?
Correct
Congrats! 4.
Incorrect
-
Question 59 of 100
59. Question
1 pointsA Scrum Master is keeping a list of open impediments, but it is growing and he has been able to resolve only a small portion of the impediments. Which techniques would be most helpful in this situation? Select three answers.
Correct
Congrats! 1. 2. 5.
Incorrect
-
Question 60 of 100
60. Question
1 pointsDuring a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
Correct
Congrats! 1.
Incorrect
-
Question 61 of 100
61. Question
1 pointsHow often should Development Team membership change?
Correct
Congrats! 3.
Incorrect
-
Question 62 of 100
62. Question
1 pointsWhat does it mean to say that an event has a time-box?
Correct
Congrats! 3.
Incorrect
-
Question 63 of 100
63. Question
1 pointsAn organization has decided to adopt Scrum, but management wants to change the terminology to fit with a terminology already used. What will likely happen if this is done?
Correct
Congrats! 4.
Incorrect
-
Question 64 of 100
64. Question
1 pointsWhen can a Development Team cancel a Sprint?
Correct
Congrats! 1.
Incorrect
-
Question 65 of 100
65. Question
1 pointsWhich of the following is not a Product Owner responsibility?
Correct
Congrats! 3.
Incorrect
-
Question 66 of 100
66. Question
1 pointsWhen does the next Sprint begin?
Correct
Congrats! 4.
Incorrect
-
Question 67 of 100
67. Question
1 pointsWho defines the Sprint Backlog scope?
Correct
Congrats! 2.
Incorrect
-
Question 68 of 100
68. Question
1 pointsWhich of the following might the Scrum Team discuss during a Sprint Retrospective?
Correct
Congrats! 4.
Incorrect
-
Question 69 of 100
69. Question
1 pointsThe most encouraged time of day to hold a Scrum Daily Meeting is…
Correct
Congrats! 1.
Incorrect
-
Question 70 of 100
70. Question
1 pointsWhat is Scrum?
Correct
Congrats! 1.
Incorrect
-
Question 71 of 100
71. Question
1 pointsIf a new requirement emerges once a Scrum project is running, it should be…
Correct
Congrats! 3.
Incorrect
-
Question 72 of 100
72. Question
1 pointsAgile methodologies think all documentation is a waste of time…
Correct
Congrats! 2.
Incorrect
-
Question 73 of 100
73. Question
1 pointsWhat is meant by Team velocity in Scrum projects?
Correct
Congrats! 2.
Incorrect
-
Question 74 of 100
74. Question
1 pointsWhat is meant by Kanban?
Correct
Congrats! 3.
Incorrect
-
Question 75 of 100
75. Question
1 pointsWhich one of the following is a key feature that you would expect to find in an Agile project?
Correct
Congrats! 3.
Incorrect
-
Question 76 of 100
76. Question
1 pointsWhat should the developers do if the product owner is repeatedly too busy to be available?
Correct
Congrats! 4.
Incorrect
-
Question 77 of 100
77. Question
1 pointsWhat does not belong to the agile manifesto’s main pillars?
Correct
Congrats! 3.
Incorrect
-
Question 78 of 100
78. Question
1 pointsPlease select which statement regarding the Refinement is the most accurate.
Correct
Congrats! 1.
Incorrect
-
Question 79 of 100
79. Question
1 pointsThe purpose of a Sprint is to produce a done increment of working product.
Correct
Congrats! 1.
Incorrect
-
Question 80 of 100
80. Question
1 pointsWho is responsible for managing the progress of work during a Sprint?
Correct
Congrats! 1.
Incorrect
-
Question 81 of 100
81. Question
1 pointsThe time-box for the Sprint Planning meeting is…
Correct
Congrats! 4.
Incorrect
-
Question 82 of 100
82. Question
1 pointsWhich of the following services are appropriate for a Scrum Master in regard to the Daily Scrum?
Correct
Congrats! 1.
Incorrect
-
Question 83 of 100
83. Question
1 pointsWhat could be a source of requirements for any changes to be made to the product?
Correct
Congrats! 1.
Incorrect
-
Question 84 of 100
84. Question
1 pointsWhat happens when a Sprint is cancelled? Select three answers.
Correct
Congrats! 1. 3. 5.
Incorrect
-
Question 85 of 100
85. Question
1 pointsScrum recommends using only those Scrum components and rules which suit most for a particular project.
Correct
Congrats! 1.
Incorrect
-
Question 86 of 100
86. Question
1 pointsWho participates in the Sprint Planning? Select three answers.
Correct
Congrats! 1. 3. 4.
Incorrect
-
Question 87 of 100
87. Question
1 pointsDefinition of “Done” is created during the first Sprint and remains unchanged until the Product release.
Correct
Congrats! 1.
Incorrect
-
Question 88 of 100
88. Question
1 pointsWho is allowed to change the Sprint Backlog during the Sprint?
Correct
Congrats! 5.
Incorrect
-
Question 89 of 100
89. Question
1 pointsWhat are Product Backlog features? Select three answers.
Correct
Congrats! 1. 3. 4.
Incorrect
-
Question 90 of 100
90. Question
1 pointsWhat are the Scrum Artifacts? Select three answers.
Correct
Congrats! 1. 2. 3.
Incorrect
-
Question 91 of 100
91. Question
1 pointsWhat comprises Scrum? Select three answers.
Correct
Congrats! 1. 3. 4.
Incorrect
-
Question 92 of 100
92. Question
1 pointsWho is required to attend the Daily Scrums?
Correct
Congrats! 3.
Incorrect
-
Question 93 of 100
93. Question
1 pointsA representative of the customer has asked the Development Team to add a very important item to an ongoing Sprint. What should they do?
Correct
Congrats! 1.
Incorrect
-
Question 94 of 100
94. Question
1 pointsThere is no one in a Scrum Team called “project manager”.
Correct
Congrats! 1.
Incorrect
-
Question 95 of 100
95. Question
1 pointsThe duration (length) of the Sprint is decided by…
Correct
Congrats! 4.
Incorrect
-
Question 96 of 100
96. Question
1 pointsWhich of the following events can not be shortened?
Correct
Congrats! 5.
Incorrect
-
Question 97 of 100
97. Question
1 pointsWhich does a self-organizing Development Team choose?
Correct
Congrats! 2.
Incorrect
-
Question 98 of 100
98. Question
1 pointsWhat things best help the Product Owner manage the value of a product? Select two answers.
Correct
Congrats! 3. 4.
Incorrect
-
Question 99 of 100
99. Question
1 pointsWhich statements are right when four teams are working on a single product? Select two answers.
Correct
Congrats! 1. 5.
Incorrect
-
Question 100 of 100
100. Question
1 pointsThe estimation method recommended by Scrum is…
Correct
Congrats! 4.
Incorrect